FRA2 Backbone Maintenance
Scheduled Maintenance Report for Equinix Metal
Completed
This maintenance has been cancelled and will be rescheduled at a later date.
Posted Aug 25, 2020 - 13:07 UTC
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Aug 25, 2020 - 13:00 UTC
Scheduled
On Tuesday, August 25, 2020 between 09:00-12:00 EST (13:00-17:00 UTC), we will conduct a non-disruptive hardware upgrade of our networking platform in the Frankfurt (FRA2) data center to new, higher capacity hardware in support of continued growth in this region.

During the upgrade, Packet engineers will shift all traffic and network services to alternate, redundant paths before initiating the hardware upgrade. The maintenance may result in a brief intermittent loss of provisioning capability, but no data plane impact is expected.

Please reach out to our support team at support@packet.com if you have any questions or concerns.
Posted Aug 21, 2020 - 13:57 UTC
This scheduled maintenance affected: Equinix Metal Network.