EWR1 Switch Software Upgrade
Scheduled Maintenance Report for Equinix Metal
Completed
The scheduled maintenance has been completed.
Posted Mar 12, 2019 - 03:54 UTC
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Mar 12, 2019 - 03:00 UTC
Scheduled
On Tuesday, March at 12 at 03:00 UTC*, Packet will perform upgrades to a pair of switches in our EWR1 (Parsippany, NJ) datacenter to bring these devices into version compliance & improve the performance and stability of our network.

During the 2-hour maintenance a switch reboot will be required, resulting in a short loss of connectivity to server instances in the affected rack.

As this event will impact only a single rack, customers with impacted server instances will receive an individual notice that includes a specific list of any affected servers.

Please feel free to reach out to us at support@packet.com with any questions.


* Time Zone Conversion:
EWR1: 3/11 at 23:00
DFW1: 3/11 at 21:00
SJC1: 3/11 at 20:00
AMS1: 3/12 at 04:00
NRT1: 3/12 at 12:00
FRA1: 3/12 at 04:00
UTC: 3/12 at 03:00
Posted Mar 11, 2019 - 05:09 UTC